  4. Chinese New Year Stops the Factory, Not the Calendar

Phase Guide

Chinese New Year Stops the Factory, Not the Calendar

The festival lasts a week. The gap in production runs from the middle of January to the middle of March, and it is planned for in November.

November 3, 2026

6 Feb 2027Published date for Chinese New Year, to be re-checked
1–3 weeksFactory closure, longer than the public holiday
4–6 weeksEffective loss of output around the closure, typical
mid-NovemberLast comfortable date to place an order for pre-holiday delivery
The inside of an empty shipping container looking toward cartons stacked at the far end
Forty feet of nothing. An empty box is what a supply chain looks like in the second week of February, when the factory is closed, the driver has gone home and the vessel sails without it. The order that fills it was decided in November.

The Shape of the Disruption

A Chinese factory does not stop for a week in February. It slows in the second week of January as workers begin to leave, pushes hard until the last working day, closes, reopens with a partial crew, and returns to normal output somewhere in the first half of March.

Add the effect on suppliers and the picture widens. A factory's component suppliers close too, and their suppliers as well, so a material ordered in the first week after the holiday may not arrive until the third. Freight has its own version: the vessels that load in late January are full, and the ones that load in the first week of March are also full, because everyone who could not ship in January ships then.

The practical total is four to six weeks of lost output for a single closure. Buyers who plan for "one week off" are the ones who discover in March that the order they placed in December has not started.

Before: The Production Push

In the six weeks before the closure, factories run at their highest output of the year and simultaneously become hardest to schedule. Two things compete for the same line: orders that must ship before the holiday, and orders placed late that the sales team accepted anyway.

What this means for a buyer with an order in production is that the date promised in November is at its most fragile in January. Completion slips are common, and the excuse is usually true: a component arrived late, or a worker's replacement was not trained.

  • Confirm the completion date in writing in early December, not January, while there is still room to move.
  • Ask for the factory's own closure notice in November. It states the last production day, the last shipping day and the reopening day, and they are three different dates.
  • Book the vessel before the goods are finished. On the pre-holiday lanes, space is the constraint, not the production.
  • Inspect early. An inspection in the last week before closure is a race against a factory that is emptying its floor.

The January Shipping Crunch

Every shipper in South China wants cargo on a vessel before the closure, and the result is the tightest booking window of the year. Rates move up, equipment gets scarce, and rollovers become normal rather than exceptional.

Three mechanisms make January harder than it looks on a schedule.

Blank sailings. Carriers reduce capacity around the holiday because they expect demand to fall afterwards. The capacity is removed on the assumption that the peak has passed, which is exactly when a late order needs it.

Cut-offs pulled forward. Documentation deadlines move earlier because the shipping lines' own offices close. A bill of lading instruction that would be accepted on the day of sailing in October has to be in two days before in late January.

Empty equipment. Containers accumulate where they are not needed and run short where they are, and a factory that cannot get a box cannot load one.

The response is a booking four to five weeks ahead, a confirmed cut-off in writing, and a trucking plan that does not depend on the last working day.

During: What Still Moves

Ports, terminals and customs operate through the holiday, usually with reduced gate hours and a thinner roster. Vessels sail. What stops is everything behind the port gate.

  • Trucking. Drivers go home too, and the ones who stay charge more. A container at a factory that closes on Friday may not reach the terminal until the following week.
  • Warehouses. Most close, and a consolidation warehouse that closes takes every buyer's cargo with it.
  • Inspectors and agents. Inspection companies book out, and a factory that is closed cannot present goods.
  • Documentation. Certificates of origin and some inspection certificates depend on offices that close.

Cargo already at the terminal and cleared for loading will sail on schedule. Cargo that is anywhere else on the last working day will wait, and it will wait longer than the holiday, because the queue to load afterwards is longer than the queue before.

After: The Return Is Uneven

Reopening day is a date on a notice, not a resumption of output. The first days go to maintenance, to restarting equipment, and to the workers who have returned.

Return rates matter more than any other single factor, and they vary by region and by factory. A plant that employs local workers reopens faster than one that depends on staff who travel a thousand kilometres home. A factory that pays a return bonus, or that arranges transport back, recovers in days rather than weeks.

Ask the question directly: what percentage of the workforce came back last year, and by when was the line at full speed. A factory that answers with numbers has been asked before, which usually means it has been through a bad year and fixed something.

Quality has its own pattern. The first batch after a restart is made by a partly new crew on machinery that has been idle. It is worth inspecting more densely than a mid-year batch, and worth telling the factory in advance that you will.

The Dates an Order Has to Hit

Work backwards from the closure. Assume the published holiday date, add the factory's own closure either side, and add the ramp.

  • Order placed by mid-November. Production finished before the January crunch, vessel booked in December, goods on the water before the closure.
  • Order placed in December. Production runs into the pre-holiday push, shipping becomes a gamble, and a rollover pushes delivery into March.
  • Order placed in January. In practice an order for after the holiday. It will be produced in late February or March, and the factory will price it without urgency.
  • Order placed in February. Production in March, arrival in April or May. Fine for summer stock, wrong for anything seasonal.

The last comfortable date is not a rule about Chinese factories, it is arithmetic about vessels and weeks. A buyer whose goods must be on a shelf in April needs the container to sail in January, which means the deposit left in November.

What to Hold, and How Much

The festival is the one annual event in the Chinese supply chain that can be forecast. That makes it the easiest to hedge, and most buyers under-hedge because the hedge costs cash in December.

The quantity to hold is the sales expected during the closure plus the sales expected before the factory returns to normal output, plus a margin for the quality of the first batch back. On a product with steady demand and a six-week sea transit, that is usually six to ten weeks of cover ordered early.

Two categories deserve separate treatment. Goods with a seasonal deadline should be produced before the closure, whatever the storage cost, because a late arrival misses the season entirely. Goods with a long shelf life and steady demand can absorb a March delivery, and paying for early production there is money spent for nothing.

The alternative to stock is a second source outside China. It costs more per unit and it exists precisely for the six weeks when the primary source cannot ship. Whether that premium is worth paying depends on what a stock-out costs, which is a question about your customer rather than about freight.

The 2027 date above is the published festival date and should be re-checked before it is used in a plan. Factory closures are longer than the public holiday and differ by company, by province and by year.

FAQ

Q When is Chinese New Year in 2027?

The festival falls on 6 February 2027 according to the published calendar, with the public holiday running across the surrounding days. Confirm the arrangement and the factory closure separately, because they are not the same window.

Q How far in advance should I place an order before Chinese New Year?

Mid-November for goods that must sail before the closure. December orders run into the pre-holiday production push and the January booking crunch, and a single rollover moves delivery into March.

Q Do Chinese factories close completely?

Most stop production. Some keep a skeleton crew for maintenance and security, and a few large exporters run partial shifts. Warehouses, trucking and inspection services largely stop.

Q Can I ship during Chinese New Year?

Ports and vessels operate. Trucking, warehousing, inspection and most documentation services do not, or run at reduced capacity. Cargo already at the terminal can sail; cargo at a factory will not move.

Q How long until production is normal again?

Two to three weeks after reopening is typical, longer where the workforce travels far. Ask the factory for last year's return rate, which is a more useful number than any promise.

Q Is it cheaper to order before or after the holiday?

Unit prices are usually similar; freight is not. Pre-holiday space is the most expensive of the year, and post-holiday space is congested. The cheapest window is often production in December with a sailing in early January.

An order that has to leave before the closure

Send the completion date and the destination and we will tell you which sailing is realistically reachable, what the cut-off is, and where the plan breaks if production slips a week.